During 2020, despite COVID-19, two disused Netball courts have been transformed into the new home of the Rowville Men’s Shed.
2 September 2020
All finished, now all we need is for Covid-19 to finish.
The view from the side yard.
The verandah overlooks the side garden.
5 August 2020
The kitchen and meeting area are nearly finished
25 July 2020
The kitchen and meeting area fitout is nearly finished.
8 July 2020
With the plasterboard on the internal walls you can better visualise the layout
24 June 2020
Internal framing is progressing.
22 June 2020
Wth internal framing starting, a couple of the Shed executive went onsite with Knox Council staff to discuss power outlet locations with the builder.
June 19 2020
The installation of the roof and skylights is now complete
12 June 2020
The Frame is up, the walls installed, now the roof is going on.
28 May 2020
The slab is nice and dry ready for the shed to arrive
27 April 2020
Concrete slab floor poured - Size is approx 12 metres X 28 metres
20 April 2020
The slab has been poured, one step closer to completion.
9 April 2020
The footings are prepared, nearly ready for the concrete to be poured.
31 March 2020
There is a guy with a gadget that locates underground services. He was mapping and marking the entire area in preparation for the sewer line that will cross from the tennis centre and Shed to the Footy pavilion’s pit.
18 March 2020
Old Netball Court surface removed
17 March 2020
Preparation work has started
2 January 2020
Work about to start
(c) 2018-21 – Rowville Men’s Shed Inc. – ABN 34 306 763 372 – P.O. Box 2113, Rowville, 3178